问题描述:
[单选]
您是公司的项目经理。项目的一部分需要生产 10,000 个小部件,您的公司将外包这些小部件。公司已同意支付所有相关成本和估计项目成本的 5%。这谈判的是哪种类型的合同?<br/>You are a project manager for your company. Part of the project requires producing 10,000 widgets, which your company will outsource. The company has agreed to pay all related costs and 5 percent of the estimated project costs. What type of contract has been negotiated?
A.成本加固定费用合同<br/>Cost-Plus-Fixed-Fee contract
B.总价合同<br/>Fixed-price contract
C.成本加激励费用合同<br/>Cost-Plus-Incentive-Fee contract
D.工料合同<br/>Time and Material contract
参考答案:查看无
答案解析:无
☆收藏
答案解析:无
☆收藏
上一篇:您刚刚开始作为项目经理进行项目。项目发起人要求您通过电子邮件和每月项目状态会议每周更新状态,以审核项目的进度。这些要求记录在以下方面( )<br/>You are just starting on a project as project manager. The project sponsor asks you for weekly status updates by email and monthly project status meetings to review the project’s progress. These requirements are documented in the( )
下一篇:卖方与买方签订了合同。 在项目结束时,卖方获得了项目成本的补偿,但根据合同中规定的某些主观标准收取了低额费用。 这可能是什么类型的合同?<br/>A seller entered into a contract with a buyer. At the end of the project, the seller was reimbursed for the cost of the project but received a low fee based on certain subjective criteria that were specified in the contract. What type of contract is this likely to be?
- 我要回答: 网友(216.73.216.135)
- 热门题目: 1.根据形状,用途对手术镊进行命 2.以下可用于夹闭肠道断端、阻断 3.以下关于柯克钳的作用正确的有